Rosebank Industrial Park
Project progress
June 2020 | Reinstatement fencing along Edwards Engineering Ltd/SH 1 boundary completed.
Street lights programmed to be installed by PowerNet mid June. NZTA approved advisory signage due to be installed once signs are manufactured and delivered to site. Slip lane is now in full use. |
November 2019 - February 2020 | Slip lane road construction. |
October - November 2019 | Chorus underground service re-location. |
24/05/2019 | Provincial Growth Fund announces they will invest $200k to help build a slip lane off State Highway One to enable large trucks and other vehicles to safely exit the highway and access the Rosebank Industrial Park. |
17/08/2018 | Public invited to help name the road by coming up with name suggestions |
26/04/18 | Work gets underway transforming the Rosebank Industrial Park |
18/10/17 | New quick sale items added |
11/02/16 | Demolition finished and new sale items added |
03/02/16 | New demolition photos uploaded |
22/10/16 | Demolition underway |
21/10/15 | Latest quick sale items added |
02/10/15 | Re-locatable buildings go on sale |
18/09/15 | Expression of interest sought for demolition - now closed |
18/09/15 | Deadline for initial business interest set |
18/09/15 | More quick sale items added |
01/09/15 | Latest quick sale items on offer |
31/08/15 | Open day at site |
21/08/15 | More quick sale items go on offer |
14/08/15 | 20 new quick sale items added |
06/08/15 | More quick sale items on offer |
29/07/15 | Quick sale items on offer |
20/07/15 | Sarah Van Asperen appointed site manager |
10/07/15 | Rosebank Industrial Site's webpage published. |
24/06/15 | Council announces purchase of site |